Table 3 Procedure and activity times (in minutes) for process steps estimated from time and motion studies. Note that the “ablation” process time is the sum of the ablation procedure and post-counseling durations, and the “VTT” process time is the sum of the VTT procedure and registration/counseling durations

From: Planning for resilience in screening operations using discrete event simulation modeling: example of HPV testing in Peru

Step

Distribution

Minimum

Most likely

Maximum

Registration and counseling

PERT

0

12.159

15.309

Self-sampling

Triangular

0

1

4.297

Ablation procedure

PERT

0

0.258

9.144

Ablation post-counseling

PERT

0

0.452

24.065

VTT procedure

PERT

0

0

96.648

VTT registration and counseling

PERT

0

3.239

18.172